Here is the proposed construction schedule (page 436 with my PDF viewer)
If I remember properly from VGC California requires a higher level of completion before sales can begin. , so the end of 2022 sounds right . Of course start date and construction progress are always subject to variances
3.0 Construction Detail
Construction Phase
Phase
Number
Phase Name Phase Type Start Date End Date Num Days
Week
Num Days Phase Description
1 Demolition Demolition 9/22/2020 12/16/2020 5 62
2 Site Preparation Site Preparation 12/17/2020 2/4/2021 5 36
3 Grading-Excavation Grading 2/5/2021 5/14/2021 5 71
4 Building Construction Building Construction 4/1/2021 1/10/2023 5 464
5 Paving Paving 1/11/2023 2/10/2023 5 23
6 Architectural Coating Architectural Coating 2/11/2023 3/15/2023 5 23
Acres of Grading (Site Preparation Phase): 18